Last reviewed: 3 September 2026

Volume formulas

All dimensions are converted to metres. Depth entered in millimetres is divided by 1,000 before it is used.

The resulting cubic metres are the primary result. The calculator does not add a hidden waste, settlement or compaction allowance.

Indicative weight coefficients

Estimated tonnes equal cubic metres multiplied by the selected coefficient. These are planning defaults, not certified measurements of a product:

As an Australian supplier cross-check, Australian Native Landscapes publishes indicative loose values including 0.3 tonnes per cubic metre for bark, 0.4 for woodchip, 1.2 for garden mix, 1.4 for topsoil, 1.3–1.5 for its listed sands, 1.45 for blue metal and 1.75 for road base. Its table also warns that grade, mineral content, moisture and source change density. See ANL's landscape product weights and volumes.

LandscapeCalc intentionally exposes its coefficients because a local supplier's conversion should replace a default whenever it is available. A difference between this calculator and a supplier is not an ordering tolerance: use the supplier's figure for that product.

Ordering equivalents and rounding

The mulch calculator also shows litres: cubic metres × 1,000. A litre is one cubic decimetre, as defined in the BIPM SI Brochure (checked 20 October 2026). If you enter a bag size in litres, the calculator divides the unrounded total litres by that size and rounds up to whole bags. The bag size comes from your product label; no retail pack size is assumed.

The 20 kg equivalent divides estimated weight in kilograms by 20 and rounds up to a whole unit. It is a mass comparison only; landscape products may instead be sold loose, by volume or in bags measured in litres.

The 1 m³ bulk-bag equivalent divides volume by one cubic metre and rounds up. Suppliers offer different bulk-bag sizes and weight limits, so this is not a retail pack count.

Cubic metres and tonnes are displayed to two decimal places; litres use up to two decimal places. The unrounded values are used before whole-unit equivalents are rounded up, with floating-point noise normalised at whole-bag boundaries.

Depth and project requirements

The depth buttons are editable starting points, not design advice. Required depth can depend on the product, intended use, subgrade, drainage, compaction and project specification. Enter the depth provided by the relevant supplier, designer, installer or approved project documentation.

Known limitations

If a formula, coefficient or source needs correction, please use the Contact page.

Feedback